ERP implementation and migration
An ERP implementation is six phases of work, and a public company reports the result to the SEC within a quarter
Vendors publish little about how long an implementation takes or what it costs. Public companies have to say when one changes their internal control. We read both.
Published , updated . 13 sources, every one listed at the foot.
Question What are the phases of an ERP implementation and how long and costly are they in practice?
ERP implementation, as Microsoft's implementation guide sets it out, runs through five stages of its Success by Design framework: strategize, initiate, implement, prepare and operate 1. Workday's deployment page, read on 22 November 2026, says Launch Express can "Go live on Workday within a ten-to-twenty plus-week time frame" and Launch Flex "in as few as twenty-seven weeks" 13.
Between January 2024 and September 2026, 1,876 quarterly reports on Form 10-Q matched one SEC EDGAR full-text query for "enterprise resource planning" and "changes in internal control over financial reporting". The sample read below shows what that count holds.
Figure 1
Six phases, with the control checkpoints each one has to pass
- 1PlanCharter, scope by module and entity, out-of-scope list Control owners named
- 2ConfigureChart of accounts, dimensions, workflows, roles Access and segregation of duties designed
- 3MigrateBalances, open items, master records, history Conversion reconciled and signed
- 4TestProcess tests, end-to-end tests, a mock close User acceptance signed by process owners
- 5Cut overFreeze, final load, go decision, rollback point Cutover access removed
- 6StabiliseFirst closes, fix backlog, control review Change in control disclosed for the quarter
Part I The six phases and what each one produces
Each paragraph below is what to ask for or decide in one of the six phases.
Plan. Write the project charter, the scope by module and entity, the named team, the budget and the go-live date. Have the CFO sign the list of what is out of scope.
Configure. Build the chart of accounts, dimensions, entities, approval workflows and user roles in a test environment. Who can post, approve and change master data? Design those roles here, against the segregation-of-duties rules your auditor will test, rather than after go-live.
Migrate data. Decide the open balances, open items (invoices, bills, purchase orders), master records and history to carry. Reconcile each conversion, trial balance in the old system against trial balance in the new one, entity by entity, and have someone who did not run the load sign it.
Test. Run unit tests of each configured process, then end-to-end tests that follow a transaction from order to cash and from purchase to payment, then a full mock close. Have the process owners sign user acceptance testing.
Cut over. Plan the freeze on the old system, the final data load, the reconciliation and the decision to go. Write the rollback plan before the weekend, with the point after which there is no rollback.
Stabilise. Track the first closes on the new system, the backlog of fixes, and whether the controls designed in configuration are operating. For a public company, which quarterly report will carry the change?
What the plan should hold before configuration starts
Give each of these lines an owner and a date:
- The legal entities, currencies and ledgers in scope at go-live, and those deferred to a later wave.
- The modules to switch on at go-live, set against the modules in the contract.
- The data to be migrated, by object (balances, open items, masters, history), with the years of history.
- Which interfaces to build to the systems that stay: banks, payroll, CRM, billing, tax.
- The reports to have on day one, named, with their owners.
- The cutover approach and the date of the first close on the new system.
- Who is back-filled, for how long, and the budget line that pays for it.
Write them down before the statement of work is signed, and give the same list to every partner that bids.
Part II Who does the work
Start with the vendor. Microsoft's implementation guide says it "is relevant for medium-sized and larger organizations" 1.
Microsoft also says it provides free online training on Microsoft Learn for the various roles in an implementation project, filtered by product and role 1. Ask every vendor the equivalent question: what training exists for your controller, your AP clerk and your system administrator, and what it costs.
Then the implementation partner: ask whether the partner is certified by the vendor, and who on its staff is named on your project.
For your own team, name who decides the design of the chart of accounts, signs off each test and reconciles each conversion. Plan for the controller and at least one senior accountant to spend a large share of their time on the project during configuration and testing, and back-fill their day jobs.
Last, the auditor: tell the audit team the go-live date early. Which conversion controls and which parts of the new access model will they test, and in which quarter?
Part III What vendors say about timelines and method
Figure 2
What two ERP vendors' own pages say about implementation
| Vendor | Method or programme named | Stages or duration stated | Implementation fee | Page read |
|---|---|---|---|---|
| Microsoft Dynamics 365 | Success by Design, used by the FastTrack for Dynamics 365 team and partners | Five stages: Strategize, Initiate, Implement, Prepare, Operate | Not stated on the page read | learn.microsoft.com implementation guide, 2026-11-11 |
| Workday | Launch Express and Launch Flex: "Fixed-fee packages that deliver value, fast" | "Go live on Workday within a ten-to-twenty plus-week time frame" (Launch Express); "Go live on Workday in as few as twenty-seven weeks" (Launch Flex) | "Defined outcome at a fixed price" (Launch Express); no amount on the page read | workday.com deployment services page, 2026-11-17 |
Microsoft's guide follows its Success by Design framework through five stages: strategize, initiate, implement, prepare and operate 1. Workday's deployment page offers "Fixed-fee packages that deliver value, fast" 13. Its Launch Express package lists a "Defined outcome at a fixed price", and Launch Flex lists "Prescribed packaging and pricing options" 13.
Ask each partner for its statement of work broken into the components the midmarket ERP guide lists.
Part IV What 10-Q filings disclose about ERP go-lives
Release 33-8238 requires a company to report each quarter any change in its internal control over financial reporting that has materially affected it, or is reasonably likely to 4.
“Under the final rules, a company must disclose any changea in its internal control over financial reporting that occurred during the fiscal quarterb covered by the quarterly reportc”
- aThe test is a change in control, and a new ledger usually changes many: who approves, what the system enforces, where records live.
- bThe disclosure is due for the quarter of the change, so the go-live date decides which report carries it.
- cForm 10-Q, Item 4, which calls for Items 307 and 308(c) of Regulation S-K.
Form 10-Q carries that disclosure in Item 4 3. The quarterly chart is SEC EDGAR full-text search, forms 10-Q, query "enterprise resource planning" "changes in internal control over financial reporting", run once per calendar quarter of filing date, counting distinct accession numbers among every result page.
Figure 3Calendar quarter of filing date
About 200 to 240 10-Q filings a quarter name an ERP beside the internal-control heading, and the count drops to about 40 in each first quarter
The 11 calendar quarters searched run from 2024 Q1 to 2026 Q3. Matching filings, the quarters summed, come to 1,876. In the April-to-December quarters, the fewest filings in a quarter was 197 and the most 236. In the January-to-March quarters, the fewest was 40 and the most 41. Form 10-Q is filed for each of the first three fiscal quarters, and no report need be filed for the fourth 3. Changes in the fourth quarter go in the annual report instead 4. The 2024 Q2 count was 197 and the 2026 Q2 count 236.
To see what the count holds, the sample took every 20th of the 234 filings of 2026 Q3 by accession number, 12 filings, and read the passage in each.
Figure 4Where the filing names an ERP
In a sample of 12 of those filings, 4 put an ERP go-live inside the internal-control disclosure
Who is in each count
- In the internal-control item (4)
- Describes an ERP go-live, rollout or monitoring as part of its internal-control disclosure (Item 4 changes, or a material-weakness remediation): A.K.A. Brands Holding Corp., Banzai International, Inc., LKQ Corporation, Solaris Energy Infrastructure, Inc.
- Elsewhere, as a project (3)
- Mentions an ERP implementation elsewhere (risk factor, forward-looking statement, management's discussion): Acushnet Holdings Corp., Bio-Rad Laboratories, Inc., SolarEdge Technologies, Inc.
- For another reason (5)
- Mentions an ERP system for another reason (costs, purchase commitments, capital spending, litigation, a rate case): Corsair Gaming, Inc., CSW Industrials, Inc., Edison International, Mangoceuticals, Inc., Warner Bros. Discovery, Inc.
Four of the 12 describe an ERP project as part of the internal-control disclosure. LKQ Corporation, under its heading on changes in internal control, reported the next step of a rollout country by country 6:
“In April 2026, in conjunction with our previously announced plana, we continued our phased rolloutb of a common Enterprise Resource Planning ("ERP") system across Europe by completing the implementation in Germanyc.”
- aThe rollout was disclosed before this quarter; each country's go-live becomes its own quarterly change.
- bOne of the three cutover choices below, chosen here by country.
- cThe change is dated to a month, which places it in the quarter the report covers.
Banzai International wrote: "During the quarter ended March 31, 2026, we implemented a new enterprise resource planning" system 7. It called the implementation "an important step in our remediation efforts" 7. Solaris Energy Infrastructure wrote that it continues "to monitor the impact of the implementation of our Enterprise Resource Planning" system on its processes and procedures 8. A.K.A. Brands listed "implement an enterprise resource planning" system among the steps of its remediation, and said its "new global ERP system is implemented across a majority of the Company's operations" 9.
Three of the 12 name an ERP implementation elsewhere, as a project. Acushnet wrote: "During 2024, we began a multi-year implementation of a new global cloud-based enterprise resource planning" platform 10. Five of the 12 mention an ERP system for another reason.
Banzai adds that "the material weaknesses will not be considered remediated until the applicable controls have operated for a sufficient period of time" 7. For a company with an open finding, how many periods of operation will its auditor want after go-live?
Part V What the cost is made of
Ask for each line of the budget on its own: the licence or subscription; the partner's fees for configuration, migration and training; your own team's time, and the cost of back-filling their day jobs; data cleansing before migration; interfaces to the systems that stay; and a contingency for the first closes.
Corsair Gaming lists, among its long-term non-cancelable purchase commitments, multi-year contractual arrangements for subscriptions to its ERP system and the related support services 11. Warner Bros. Discovery counts transformative system implementations, such as ERP systems, among its integration costs and says they may take several years to complete 12.
Ask each partner for a fixed fee by phase with the assumptions written down, and ask the vendor what the subscription costs in year two, after the users and modules switched on during the project are counted.
Part VI Cutover: big bang, phased or parallel
Big bang. Will every entity and process move on one date, with one conversion, one cutover weekend and one set of training? If the first close fails, what is the fallback for every entity at once?
Phased. LKQ wrote of a "phased rollout of a common Enterprise Resource Planning" system across Europe 6. How long will two systems run side by side, and which interfaces join them in the meantime? For a public company, in how many consecutive quarters will a change in internal control be reported?
Parallel run. Will the old and new systems both run for a period, with the results compared? How many closes, or which entities, does the double entry cover?
Choose before configuration starts, and set the data migration plan, the interfaces and the test plan from the choice.
Part VII After go-live: stabilisation and the first close
Plan the first close on the new ERP with more days than the last close on the old one. Hold the old system read-only, keep the conversion reconciliations with the close file, and run the user-access report on day one and again after the first close, removing the roles granted for the cutover weekend.
Write down which controls changed, with dates, while the project team is still in the room. Which of them materially affected, or are reasonably likely to materially affect, internal control, and so belong in the next quarterly report 4? Will a private company's auditor ask for the same list at year end?
Part VIII Where to go from here
See ERP selection and the midmarket and enterprise ERP guides.
How the figures here were made: the quarterly counts are SEC EDGAR full-text search, forms 10-Q, run once per calendar quarter of filing date, counting distinct accession numbers among every result page. The sample is 12 filings drawn from the 2026 Q3 results (every 20th by accession number), each read on sec.gov and put in one class.
Sources
- Microsoft Learn, Dynamics 365 implementation guide. learn.microsoft.com/
en-us/ dynamics365/ guidance/ implementation-guide/ overview, read . - SEC EDGAR full-text search. efts.sec.gov/
LATEST/ search-index?q=%22enterprise%20resource%20planning%22%20%22changes%20in%20internal%20control%20over%20financial%20reporting%22&forms=10-Q, read . - SEC, Form 10-Q general instructions. sec.gov/
files/ form10-q.pdf, read . - Federal Register (GovInfo), 68 FR 36635 (SEC Release 33-8238). govinfo.gov/
content/ pkg/ FR-2003-06-18/ html/ 03-14640.htm, read . - SEC, Release 33-8238 (rule release page). sec.gov/
rule-release/ 33-8238, read . - LKQ Corporation, Form 10-Q for the quarter ended 30 June 2026 (SEC EDGAR). sec.gov/
Archives/ edgar/ data/ 1065696/ 000106569626000044/ lkq-20260630.htm, read . - Banzai International, Inc., Form 10-Q for the quarter ended 30 June 2026 (SEC EDGAR). sec.gov/
Archives/ edgar/ data/ 1826011/ 000119312526352362/ para-20260630.htm, read . - Solaris Energy Infrastructure, Inc., Form 10-Q for the quarter ended 30 June 2026 (SEC EDGAR). sec.gov/
Archives/ edgar/ data/ 1697500/ 000162828026054349/ sei-20260630.htm, read . - A.K.A. Brands Holding Corp., Form 10-Q for the quarter ended 30 June 2026 (SEC EDGAR). sec.gov/
Archives/ edgar/ data/ 1865107/ 000186510726000044/ aka-20260630.htm, read . - Acushnet Holdings Corp., Form 10-Q for the quarter ended 30 June 2026 (SEC EDGAR). sec.gov/
Archives/ edgar/ data/ 1672013/ 000167201326000158/ golf-20260630.htm, read . - Corsair Gaming, Inc., Form 10-Q for the quarter ended 30 June 2026 (SEC EDGAR). sec.gov/
Archives/ edgar/ data/ 1743759/ 000119312526337981/ crsr-20260630.htm, read . - Warner Bros. Discovery, Inc., Form 10-Q for the quarter ended 30 June 2026 (SEC EDGAR). sec.gov/
Archives/ edgar/ data/ 1437107/ 000143710726000075/ wbd-20260630.htm, read . - Workday, deployment services page. workday.com/
en-us/ services/ deployment.html, read .
bestfinancesoftware.com/guides/erp-implementation. Published .